It is also possible to use the uncertainty module in Openwind to suggest additional sites for meteorological masts to extend the wind monitoring campaign such that the uncertainty of the project as a whole is minimized.
With all the current met masts as children of the site WRG, right-click on the WRG and select "Suggest New Masts".
In order to make good use of this function, it is necessary to limit the valid area of the WRG to areas in which turbines are likely to be placed (requires the WRG to be able to access a SiteLayer), or to a project area (by setting the project area as a child of the WRG and setting up the appropriate layer logic).